NEP & NZT Project — Isolating Joint Seal Qualification
01Energy · Elastomer seal qualification

NEP & NZT Project — Isolating Joint Seal Qualification

Saipem (via EQUA) · Element Materials Technology, Hitchin · Oct–Nov 2026
  • Third-party witness of Rapid Gas Decompression (RGD) testing to API 17J and thermal ageing to ISO 23936-1 for monolithic isolating-joint seals
  • Verified specimen identification, tensile dumbbells and RGD plaques against advice notes and approved test procedures
  • Witnessed hardness, density and tensile testing of aged specimens; checked calibration traceability to UKAS ISO/IEC 17025
  • Issued inspection reports with photo records and raised test-schedule discrepancies for clarification
API 17JISO 23936-1ISO 37UKAS ISO/IEC 17025
Valve O-ring RGD & Ageing Qualification Programme
02Oil & Gas · Valve O-ring qualification

Valve O-ring RGD & Ageing Qualification Programme

For a European valve manufacturer · Element Materials Technology, Hitchin · Aug–Sep 2026
  • Witnessed an 8-cycle RGD programme (100% CO2, 320 bar, 100 °C, 20 bar/min decompression) to ISO 23936-2 / NORSOK M-710
  • Monitored ageing at 97 °C, 112 °C and 127 °C, including vessel opening, specimen removal and post-exposure checks
  • Witnessed density, Shore hardness, dimensional and tensile testing; carried out O-ring damage assessment of blistering and cracking
  • Issued daily flash reports and weekly inspection reports; agreed a recovery plan with the laboratory after system downtime
ISO 23936-2NORSOK M-710RGDDaily flash reports
Final Inspection — Clean-Agent Fire Suppression Package
03Oil & Gas · Fire & gas protection

Final Inspection — Clean-Agent Fire Suppression Package

Via Applus for a global oilfield services company · Great Yarmouth, Norfolk · Sep 2026
  • Lead inspector for witnessed final inspection of fire suppression cylinders and ancillary hardware for a gas plant in Iraq
  • Checked assembled cylinders, hoses, valves and fittings against the purchase order and approved documentation
  • Verified certification and MDR documents, packing and marking prior to release
  • Produced the inspection quality report with photographic record and punch list
Final inspectionMDR reviewPacking & marking
Supplier Inspection — Air Scour Blower Drive Motors
04Water treatment · Rotating equipment

Supplier Inspection — Air Scour Blower Drive Motors

For an EPC contractor's water treatment package · Gloucestershire · Sep 2026
  • Attended ITP stages 9.1–9.3 for 30 kW IE3 drive motors at the blower package sub-supplier
  • Verified motor nameplate data, serial numbers and tag numbers against the purchase order and datasheet
  • Checked motor-to-blower assembly, coupling arrangement and general workmanship
  • Issued the supplier inspection report against the notification of inspection
ITP stagesNameplate verificationRotating equipment
PVOC Pre-Shipment Source Inspection
05Export · HVAC equipment

PVOC Pre-Shipment Source Inspection

HVAC equipment manufacturer, Norfolk · On behalf of HQTS for an EPC contractor · Oct 2026
  • Inspected crated HVAC equipment prior to export under a PVOC conformity programme
  • Verified quantities, markings, crate labels and packing against shipping documents
  • Produced a full inspection report and 14-photo evidence sheet
PVOCPre-shipmentPacking & marking
Pre-Shipment Inspection — Industrial Marquee Cleaning Machine
06Industrial equipment · Pre-shipment

Pre-Shipment Inspection — Industrial Marquee Cleaning Machine

On behalf of HQTS · Sep 2026
  • 100% pre-shipment inspection of a refurbished marquee cleaning machine before export
  • Functional running test of drives, blower, pumps and controls; checked guarding and safety labelling
  • Verified filter housings, accessories and spares against the quotation and packing list
  • Issued the PSI report with checklist, photographs and video record — all items rated pass
PSIRunning testAccessories & packing
Qatar North Field Project — Air Handling Unit FAT
07Energy · HVAC

Qatar North Field Project — Air Handling Unit FAT

Saipem (via Denis Inspection) · HVAC vendor works, Kent · Dec 2024
  • Witnessed Factory Acceptance Testing of air handling units for offshore living-quarters HVAC systems
  • Dimensional, visual and coating checks against GA drawings, datasheets and the approved ITP
  • Witnessed fan speed, airflow, noise and electrical tests, including insulation-resistance and continuity checks
  • Reviewed coil leakage, material and calibration certificates; raised and tracked punch-list items to closure
FATITP stagesInsulation resistancePunch list